16:47-4.5 Access permit applications
(a) The maximum time frames for the review of various types of applications are summarized below. They are for the Department only and do not include any applicant time or time for Federal Highway Administration reviews of work on interstate highways, interchanges, or ramps. The Department's check of the completeness of an application is included in these timeframes.
DEPARTMENT TIME FOR APPLICATIONS
ACCEPTED FOR REVIEW (IN DAYS)
Major With
Planning
Form Minor[fn1] Major Review
Single Family Residential
Driveway MT-32 35 NA NA
Residence and Business
Driveway MT-32 35 NA NA
Minor MT-32 35 NA NA
Government Driveway MT-32 35 90 90
Major Use MT-32 NA 90 90
Street Intersection MT-160 35 90 90
Concept Reviews MT-32 NA 90 90
Street Improvement MT-158 35 NA NA
Lot Consolidation or
Subdivision MT-155 NA 50 NA
Temporary Access Permit No form # 35 NA NA
[fn1] If a traffic signal is involved, the review may take 45 additional days.
Notes: (NA means Not Applicable)
(b) The time for the Department review of an application may be extended with the written consent of the applicant.
(c) When an applicant fails to respond to a Department request for information within 90 days of the request, the application shall be considered withdrawn.
Amended by R. 1993 d. 524, effective November 1, 1993. See: 25 N.J.R. 3129(a), 25 N.J.R. 4915(b). Amended by R. 1997 d. 165, effective April 7, 1997. See: 28 N.J.R. 3731(a), 28 N.J.R. 4383(a), 29 N.J.R. 1353(a). In (a), added "Temporary Access Permit", and in the table deleted footnote 1 and recodified footnote 2 as footnote 1; deleted (c) relating to pre-applications conferences; and recodified (d) as (c).