PREVIOUS SECTION | Go back to sections | Go back to the chapter | Go back to the N.J. Statutes homepage | NEXT SECTION |
New Jersey Statutes, Title: 48, PUBLIC UTILITIES
Chapter 13: Entry on lands for preliminary surveys
Section: 48:13-13: Time of commencement and completion of sewerage system
Every sewerage company organized under the laws of this State shall commence the construction of the proposed system of sewerage within 6 months from the date of its organization, and shall complete the same within 3 years from the date of commencement. The conditions annexed to the consent of the corporate authorities may designate a shorter period for the completion of such works.
Amended by L.1962, c. 198, s. 162.
This section added to the Rutgers Database: 2012-09-26 13:37:55.
Older versions of 48:13-13 (if available):
Court decisions that cite this statute: