New Jersey Statutes, Title: 40A, MUNICIPALITIES AND COUNTIES

    Chapter 11:

      Section: 40A:11-19: Liquidated damages; void provisions as to contractor's remedies

           19. Any contract made pursuant to P.L.1971, c.198 (C.40A:11-1 et seq.) may include liquidated damages for the violation of any of the terms and conditions thereof or the failure to perform said contract in accordance with its terms and conditions, or the terms and conditions of P.L.1971, c.198 (C.40A:11-1 et seq.). Notwithstanding any other provision of law to the contrary, it shall be void, unenforceable and against public policy for a provision in a contract entered into under P.L.1971, c.198 (C.40A:11-1 et seq.) to limit a contractor's remedy for the contracting unit's negligence, bad faith, active interference, tortious conduct, or other reasons uncontemplated by the parties that delay the contractor's performance, to giving the contractor an extension of time for performance under the contract. For the purposes of this section, "contractor" means a person, his assignees or legal representatives with whom a contract with a contracting unit is made.

L.1971,c.198,s.19; amended 1999, c.440, s.28; 2001, c.206, s.1.



This section added to the Rutgers Database: 2012-09-26 13:37:52.






Older versions of 40a:11-19 (if available):



Court decisions that cite this statute: CLICK HERE.